The procedure for deploying network devices in the scenario without the NMS is as follows:
1.
According to the user's FTTx service plan and the corresponding OLT version, the
commissioning engineer performs the data plan for the OLT and ONU.
2.
The hardware installation engineer draws the ONUs and sends them to the destination sites,
and then performs hardware installation, wiring, and power-on operations at the destination
sites.
3.
The hardware installation engineer checks the running status of the ONU that is installed
and powered on.
There are two LEDs, namely Link and Auth, on the ONU.
l
If the Link LED is on, it indicates that the upstream optical path is through.
l
If the Auth LED is blinking, it indicates that the ONU is registering.
l
If the Auth LED is always on, it indicates that the ONU registers successfully.
4.
After confirming that the ONU works in the normal state (the Link LED is on and the Auth
LED blinks), the hardware installation engineer records the ONU SN and reports the SN
to the commissioning engineer.
5.
According to the data plan of the OLT and ONU, the commissioning engineer configures
data on the OLT.
6.
The commissioning engineer enables the auto-discovery function of the OLT for the ONU.
7.
The commissioning engineer adds the ONU to the OLT according to the data plan of the
OLT and ONU and the SN reported by the hardware installation engineer.
8.
The commissioning engineer configures the management IP address of the ONU through
the OLT.
9.
The commissioning engineer telnets to the ONU according to the management IP address
of the ONU to configure the services for the ONU.
SmartAX MA5616 Multi-service Access Module
Configuration Guide
1 Deploying Network Devices
Issue 04 (2011-10-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6