How to activate the PC manual control:
1. If an online connection to the inverter has not been established yet:
Go online.
2. Select the
Application parameters
tab from the
Workspace
.
3. Go to the
Overview
dialog level and click the "
PC manual control
" button.
• First, the following safety note is displayed:
• Click the
Cancel
button to abort the action and close the dialog box.
• The
Timeout monitoring
input field serves to adapt the timeout time for the connection
monitoring between PC and inverter.
4. To acknowledge the note and activate PC manual control:
Click the
Activate PC manual control
button.
• The inverter is inhibited via device command (
).
• The
PC manual control
operator dialog is displayed.
Note!
With active PC manual control:
The online connection between PC and controller is monitored by the inverter.
• If the online connection is interrupted longer than the timeout time set (Lenze
setting: 2 s):
• The error response "Fault" takes place, i.e. the motor becomes torqueless and
coasts, if it has not yet been in standstill.
• The "
Ck16: Time overflow manual control
" error message is entered into the
logbook.
PC manual control provides the
Motion Control Kernel
and the motor interface with all
required control signals and setpoint signals.
• The available application (function block interconnection) is now decoupled from
these interfaces, but is continued to be processed and remains unchanged.
• It does not matter what type of motor control is set in