Installation
SuperTrak™ GEN3 System Operation and Maintenance Manual
73
Rev. 9 (12-2021)
18. Add four (4) bolts to the bottom of each electrical box, making sure the
grounding cables are secured to locations indicated by grounding symbol
stickers.
19. Lift the SuperTrak conveyance platform into position.
Use correct lifting techniques with straps and a forklift.
20. Secure the base plate to the mounting frame.
21. Install the pallets.
22. If required, fine-adjust the v-rails.
Summary of Contents for SuperTrak GEN3
Page 1: ...Rev 9 December 2021...
Page 2: ......
Page 3: ...SuperTrak GEN3 Conveyance Platform Modular Conveyor Operation and Maintenance Manual...
Page 6: ......
Page 12: ...This page is intentionally blank...
Page 30: ...This page is intentionally blank...
Page 58: ...This page is intentionally blank...
Page 296: ...This page is intentionally blank...
Page 300: ...This page is intentionally blank...
Page 364: ...This page is intentionally blank...
Page 366: ...This page is intentionally blank...