HX7+ ASD Installation and Operation Manual
25
Power Connection Requirements
Connect the 3-phase input power of the correct voltage to the input terminals of the ASD at
R/L1
,
S/L2
,
and
T/L3
(see
for the typical electrical connection scheme and
for the
terminal locations).
Connect the output of the ASD to the motor from the ASD terminals
U/T1
,
V/T2
, and
W/T3
. The input
and output conductors and terminal lugs used shall be in accordance with the requirements listed in the
section titled
Voltage/Current and Thermal Specifications on pg. 230
.
Install a molded case circuit breaker (MCCB) or fuse between the 3-phase power source and the ASD in
accordance with the fault current setting of the ASD and the
NEC
Article 430
.
The ASD is designed and tested to comply with UL Standard 508C. Modifications to the ASD system
may disqualify the UL rating.
As a minimum, the installation of the ASD shall conform to the
NEC
Article 110
, the
Occupational
Safety and Health Administration
requirements, and to any other local and regional industry codes
and standards.
Note:
In the event that the motor rotates in the wrong direction when powered up, reverse
any two of the three ASD output power leads (U, V, or W) connected to the motor.
Figure 5. HX7+ ASD/Motor Typical Connection Diagram.
CAUTION
Summary of Contents for HX7+ ASD
Page 2: ...DN 67017 001 February 2014 HX7 ASD Installation Operation Manual ...
Page 227: ...218 HX7 ASD Installation and Operation Manual Figure 35 200 kVA Sine Wave NEMA 1 Enclosure ...
Page 231: ...222 HX7 ASD Installation and Operation Manual Figure 39 200 kVA Sine Wave NEMA 3R Enclosure ...
Page 235: ...226 HX7 ASD Installation and Operation Manual Figure 43 66 163 kVA 18 Pulse Enclosure ...
Page 236: ...HX7 ASD Installation and Operation Manual 227 Figure 44 200 kVA 18 Pulse Enclosure ...
Page 237: ...228 HX7 ASD Installation and Operation Manual Figure 45 260 518 kVA 18 Pulse Enclosure ...
Page 238: ...HX7 ASD Installation and Operation Manual 229 Figure 46 518 700 kVA 18 Pulse Enclosure ...