Issue 1.2
UNIVERGE SV9100
3 - 60
Installing the SV9100 Chassis
3.
Align bolt holes in CHS BASE UNIT (see figure below) with holes
drilled in floor and secure using four anchor bolts.
4.
Align and install the CHS LARGE BATT BOX on top of the CHS BASE
UNIT.
5.
Secure the CHS LARGE BATT BOX to the CHS BASE UNIT using the
CHS2UG JOINT BRACKET KIT. Refer to figure below.
6.2.2
Battery Installation
1.
Loosen screw on front of CHS LARGE BATT BOX.
2.
Swing cover outward and detach from CHS LARGE BATT BOX.
Figure 3-79 Installing the CHSG LARGE BATT BOX using the CHS2UG JOINT BRACKET KIT
Figure 3-80 Removing CHSG LARGE BATT BOX Cover
Summary of Contents for Univerge SV9100
Page 1: ...System Hardware Manual Issue 1 2 January 2015...
Page 2: ...THIS PAGE INTENTIONALLY LEFT BLANK...
Page 40: ...Issue 1 2 UNIVERGE SV9100 1 16 Introduction to SV9100...
Page 105: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 3 33 Figure 3 42 Brackets Small Batt Box...
Page 154: ...Issue 1 2 UNIVERGE SV9100 3 82 Installing the SV9100 Chassis...
Page 239: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 4 85 Figure 4 24 Control Signal Connection...
Page 259: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 4 105 NOTES...
Page 260: ...Issue 1 2 UNIVERGE SV9100 4 106 Installing the SV9100 Blades...
Page 412: ...Issue 1 2 UNIVERGE SV9100 5 152 Installing DT Series Digital and IP Multiline Terminals...
Page 476: ...Issue 1 2 UNIVERGE SV9100 6 64 Installing SV9100 Optional Equipment...