figure below.
2.
Line up the Rack Mount Bracket(s) with the pre-drilled holes on each side of
the 19” chassis.
3.
Secure the brackets to the chassis using the supplied screws. Refer to figure
below for the 19” chassis.
Repeat for additional chassis mounting.
4.
Carefully slide the chassis into desired location in the rack. Make sure the
hooks on the mounting bracket are inserted into the back of the chassis,
Stacking additional chassis (without rack mount brackets) on top
of one rack mounted chassis is not recommended.
Figure 3-65 CHS2UG Rack Mount Brackets
Figure 3-66 Rack Mount Bracket Installed 19” CHS2UG
Summary of Contents for Univerge SV9100
Page 1: ...System Hardware Manual Issue 1 2 January 2015...
Page 2: ...THIS PAGE INTENTIONALLY LEFT BLANK...
Page 40: ...Issue 1 2 UNIVERGE SV9100 1 16 Introduction to SV9100...
Page 105: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 3 33 Figure 3 42 Brackets Small Batt Box...
Page 154: ...Issue 1 2 UNIVERGE SV9100 3 82 Installing the SV9100 Chassis...
Page 239: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 4 85 Figure 4 24 Control Signal Connection...
Page 259: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 4 105 NOTES...
Page 260: ...Issue 1 2 UNIVERGE SV9100 4 106 Installing the SV9100 Blades...
Page 412: ...Issue 1 2 UNIVERGE SV9100 5 152 Installing DT Series Digital and IP Multiline Terminals...
Page 476: ...Issue 1 2 UNIVERGE SV9100 6 64 Installing SV9100 Optional Equipment...