16.
Insert tabs on cover into holes on CHS LARGE BATT BOX. Slide the
cover left until seated and tighten the screw.
6.2.3
CHS LARGE BATT BOX to CHS2UG Connection
1.
Power down the CHS2UG chassis.
2.
Disconnect AC power cable from rear of chassis.
3.
Remove fan access panel from rear of CHS2UG chassis.
Figure 3-87 Installing Cover Battery
Ensure the CHS2UG chassis is powered OFF.
Figure 3-88 Removing Fan Access Panel
Summary of Contents for Univerge SV9100
Page 1: ...System Hardware Manual Issue 1 2 January 2015...
Page 2: ...THIS PAGE INTENTIONALLY LEFT BLANK...
Page 40: ...Issue 1 2 UNIVERGE SV9100 1 16 Introduction to SV9100...
Page 105: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 3 33 Figure 3 42 Brackets Small Batt Box...
Page 154: ...Issue 1 2 UNIVERGE SV9100 3 82 Installing the SV9100 Chassis...
Page 239: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 4 85 Figure 4 24 Control Signal Connection...
Page 259: ...UNIVERGE SV9100 Issue 1 2 System Hardware Manual 4 105 NOTES...
Page 260: ...Issue 1 2 UNIVERGE SV9100 4 106 Installing the SV9100 Blades...
Page 412: ...Issue 1 2 UNIVERGE SV9100 5 152 Installing DT Series Digital and IP Multiline Terminals...
Page 476: ...Issue 1 2 UNIVERGE SV9100 6 64 Installing SV9100 Optional Equipment...