Appearance, Specifications, and Name
3.1.3 Material Preparations
Materials are classified to Huawei-provided, self-purchased, and onsite prepared materials,
which are marked as mandatory, optional, and engineering purchasing in this document.
Mandatory: materials that are provided by Huawei and can be found in the delivered
fittings.
Optional: materials that can be purchased from Huawei or any other vendor (if you have
ordered the materials from Huawei, you do not need to purchase them elsewhere). For
details about the specifications of such materials to be purchased, see the following
sections.
Engineering procurement: materials that are not configured by Huawei and need to be
purchased from another vendor.
3.1.3.1 Water Inlet Pipe of the Wet Film Humidifier
The water inlet pipe of the wet film humidifier can be connected in two ways. Determine the
pipe routing method based on site conditions.
Figure 3-4
Connecting a water inlet pipe
(1) Connector with inner screw
thread: G 1/2 inch (reserved
device port)
(2) Rigid pipe conversion adapter: G 1/2 inch;
connected to a rigid pipe through outer screw threads
(engineering purchasing)
(3) Rigid pipe: made of PP-R
(4) Pagoda conversion adapter: G 1/2 inch; connected