GBC StreamWire
07/23/2020
RTPS
2-22
RTP 3.3.1 First jammed sheet before Steering module
Follow the below procedure when the first jammed sheet is before the
Steering module
1. Raise the top cover and check for any obstructions in the paper path
leading to the steering module
This clears the fault
Yes
- Return to normal operation
No
- Go to Step 2
2. Do GP 6.4.1 to check sensor S1
This clears the fault
Yes
- Return to normal operation
No
- Go to Step 3
3. Do GP 6.5.1 to check transport motor M1, M16 and M17.
This clears the fault
Yes
- Return to normal operation
No
- Go to Step 4
4. Inspect Solenoids L2 and L3 (GP 6.6.1)- ensure these solenoids are
not disengaging the rollers N1 and N2 when not actuated. The rollers
should extend past the metal plate, and should be even with the rest
of the idler rollers on the Upper Transport.
Rollers are not disengaged when L2 and L3 are not actuated
Yes
- Go to Step 5
No
- If N1 does not engage and disengage, replace L2 (REP 2.19)
If N2 does not engage and disengage, replace L3 (REP 2.19)
5. Inspect rollers N1, N2 and N3- GP 6.14
This clears the fault
Yes
- Return to normal operation
No
- Go to Step 6
6. Inspect the paper transport latch, if necessary perform adjustment.
Ensure the paper transport is securely closed.
This clears the fault
Yes
- Return to normal operation
No
- Go to Step 7
7. Inspect the transition from the entrance section to the Steering
module section. The steering module lower panel and the Entrance
section lower panel should be in line with each other.
The panels are in line with each other
Yes
- Go to Step 8
No
- Do REP 2.21 to remove and replace the Steering Module.
Inspect the Steering Module for damage, and re-check the Steering
Module after installation.
8. Do GP 6.3.5 FIRMWARE UPGRADE Procedure to Re-flash the
firmware for eWire.
This clears the fault
Yes
- Return to normal operation
No
- Escalate to second level
Summary of Contents for StreamWire
Page 9: ...GBC StreamWire 07 23 2020 Service Manual ix Notes...
Page 87: ...GBC StreamWire 07 23 2020 RTPS 2 72 Notes...
Page 89: ...Book Quality 07 23 2020 GBC StreamWire 3 2 This page intentionally left blank...
Page 428: ...GBC StreamWire 12 18 2018 Wiring Data 7 3 o System Wiring...
Page 429: ...Wiring Data 12 18 2018 GBC StreamWire 7 4 o Element Feeder Module...
Page 430: ...GBC StreamWire 12 18 2018 Wiring Data 7 5 o Element Transfer Module...
Page 431: ...Wiring Data 12 18 2018 GBC StreamWire 7 6 o Knife Module...
Page 432: ...GBC StreamWire 12 18 2018 Wiring Data 7 7 o Closer Module...
Page 433: ...Wiring Data 12 18 2018 GBC StreamWire 7 8 o Holder Module...
Page 434: ...GBC StreamWire 12 18 2018 Wiring Data 7 9 o Book Drawer...
Page 435: ...Wiring Data 12 18 2018 GBC StreamWire 7 10 o Paper Transport Module...
Page 436: ...GBC StreamWire 12 18 2018 Wiring Data 7 11 o Sheet Tappers Module...
Page 437: ...Wiring Data 12 18 2018 GBC StreamWire 7 12 o Deflector Module...
Page 438: ...GBC StreamWire 12 18 2018 Wiring Data 7 13 o Stacker Module...
Page 439: ...Wiring Data 12 18 2018 GBC StreamWire 7 14 o Alignment Module...
Page 440: ...GBC StreamWire 12 18 2018 Wiring Data 7 15 o Interlock AC and LCD Connections...
Page 442: ...Installation Instructions 03 26 2019 GBC StreamWire 8 2 This page intentionally left blank...