2. Start up and Adjustment Procedure
2.1 Confirmation of Connections
III
-4
2. Start up and Adjustment Procedure
2.1 Confirmation of Connections
Refer to Connection Manual (BNP-B2335) to confirm the connection of each unit and communication
terminals, etc.
Especially confirm the position of the input power and connection connectors, etc.
It is recommended to leave the servomotor and spindle motor drive lines disconnected until the
settings of the parameters, etc., is completed.
CAUTION
Ground the signal cables to ensure stable system operation. Also ground the control unit main
frame, power distribution panel and machine to one point, so they all have the same potential.
2.2 Setting of Various Switches
1) Control unit setting switch
A slide switch (SW1) and rotary switches (CS1, CS2) are located in the window on the upper front
of the control unit.
Set SW1 to the "lower side" and CS1 to "0". CS2 is normally set to "0". Refer to the following
settings if needed.
Switch
Operation
Application
0
Normal operation mode
Normal operation
1
PLC program stop
For PLC development work
2
3
4
5
6
Maintenance mode for maker
Do not use.
7
The entire memory will be erased, so do not set this. Do not use.
8 ~ F
Maintenance mode for maker
Do not use.
CAUTION
!
If the control unit's rotary switch is set to "7", all data in the NC will be erased and the system
will not start up.
Summary of Contents for EZMotion-NC E60 Series
Page 1: ......
Page 15: ...I OPERATION SECTION ...
Page 361: ...II MACHINE OPERATION MANUAL ...
Page 399: ...III SETUP ...
Page 472: ...IV APPENDIXES ...
Page 510: ......