262
Learning Advanced Features
Run Easy Start On to easily setup the basic motor parameters required to operate a motor in a
batch. Set CNF-61 (Easy Start On) to ‘1 (Yes)’ to activate the feature, initialize all parameters by
setting CNF-40 (Parameter Init) to ‘1 (All Grp)’, and restart the inverter to activate Easy Start On.
Group Code Name
LCD Display
Parameter Setting
Setting Range
Unit
CNF
61
Parameter easy start
settings
Easy Start On 1
Yes
-
-
Code
Description
CNF-61
Easy Start
On
Follow the procedures listed below to set the easy start on parameters.
No
Procedures
1
Set CNF-61 (Easy Start On)
to ‘1(Yes)’.
2
Select
‘
1 (All Grp)’ in CNF-40
(Parameter Init) to initialize all parameters
3
Restarting the inverter will activate Easy Start On. Set the values in the following
screens on the Keypad. To escape from Easy Start On, press the [ESC] key.
•
Start Easy Set: Select ‘Yes’.
•
CNF-43: Select a macro.
•
BAS-10 60/50 Hz Sel: Set motor rated frequency.
•
DRV-14 Motor Capacity: Set motor capacity.
•
BAS-13 Rated Curr: Set motor rated current.
•
BAS-15 Rated Volt: Set motor rated voltage.
•
BAS-11 Pole Number: Set motor pole number.
•
BAS-19 AC Input Volt: Set input voltage.
•
PRT-08 Select start at trip reset
•
PRT-09 Retry Number: Sets the number of restart trial when
performing a trip reset.
•
COM-96 PowerOn Resume: Sets the serial communication restart
function.
•
CON-71 SpeedSearch: Set SpeedSearch.
•
DRV-06 Cmd Source: Set command source.
•
DRV-07 Freq Ref Src: Set Frequency Reference source.
•
AP3-01 Now Date : Set the current date.
•
AP3-02 Now Time : Set the current time.
When the settings are complete, the minimum parameter settings on the motor
have been made. The Keypad will return to a monitoring display. Now the motor
Summary of Contents for 6731001500
Page 1: ......
Page 17: ...Preparing the Installation 4 37 90kW 3 Phase ...
Page 18: ...Preparing the Installation 5 110 132kW 3 Phase ...
Page 19: ...Preparing the Installation 6 160 185kW 3 Phase ...
Page 20: ...Preparing the Installation 7 220 250kW 3 Phase ...
Page 21: ...Preparing the Installation 8 315 400kW 3 Phase ...
Page 22: ...Preparing the Installation 9 500kW 3 Phase ...
Page 34: ...21 Installing the Inverter 400 V 220 500kW ...
Page 50: ...37 Installing the Inverter Inputand OutputControlTerminalBlockWiringDiagram 5 5 90kW ...
Page 66: ...Perform BasicOperations 53 ...
Page 106: ...93 Learning BasicFeatures 0 10V InputVoltageSettingDetails V1 Quantizing ...
Page 107: ...94 Learning BasicFeatures ...
Page 187: ...174 Learning Advanced Features PIDCommandBlock ...
Page 188: ...175 Learning Advanced Features ...
Page 189: ...176 Learning Advanced Features PIDFeedbackBlock ...
Page 190: ...177 Learning Advanced Features PIDOutputBlock ...
Page 191: ...178 Learning Advanced Features PIDOutputModeBlock ...
Page 205: ...192 Learning Advanced Features EPID1Controlblock ...
Page 206: ...193 Learning Advanced Features EPID2Controlblock ...
Page 228: ...215 Learning Advanced Features ...
Page 244: ...231 Learning Advanced Features TheTime Chartfor the Exception Day ...
Page 260: ...247 Learning Advanced Features SpeedSearchOperation SettingDetails ...
Page 405: ...392 RS 485 Communication Features 7 3 9 2 Control Area Parameter Read Write ...
Page 555: ...Table ofFunctions 542 8 16 4 CoolingTower MC4 Group ...
Page 558: ...Tableof Functions 545 8 16 5 Circulation Pump MC5 Group ...
Page 562: ...Tableof Functions 549 8 16 6 Vacuum Pump MC6 Group ...
Page 588: ...575 Troubleshooting ...
Page 608: ...TechnicalSpecification 595 11 3 External Dimensions 0 75 30kW 3 phase 37 90kW 3 phase ...
Page 609: ...TechnicalSpecification 596 110 185kW 3 phase ...
Page 632: ...TechnicalSpecification 619 400 V 37 500 kW Current Derating Rate ...
Page 643: ...630 ...
Page 644: ...631 ...
Page 645: ...632 ...