CLG835H
Removal and installation of work implement system
Replacement of boom shaft bushing
Figures
Operation instruction
Tools
Replace the boom bushing
1. Remove seal rings (3, 6)
with a straight screwdriver
Straight
screwdriver
2. Knock frame bushing (2),
boom bushing (4) and
bushing (5) out in sequence
with bushing knocking
tooling and sledge hammer.
Shaft bushing
knocking tooling,
sledge hammer
3. Put new frame bushing (2),
boom bushing (4) and
bushing (5) into liquid
nitrogen for freezing until
there is not a lot of smoke
coming out.
Liquid nitrogen,
hook fixture
4. Install frozen frame shaft
bushing (2), boom shaft
bushing (4) and shaft
bushing (5) into the boom
(1) in sequence with shaft
bushing knocking tooling
and sledge hammer, and
reserve mounting position
for seal rings on both sides.
Shaft bushing
knocking tooling,
sledge hammer
5. Knock seal rings (3, 6) into
the boom (1) gently with
copper bar
Copper bar
P18S00053
1. Boom
2. Frame bushing
3. Boom bushing
4. Bushing
5. Seal ring
Summary of Contents for CLG835H
Page 2: ......
Page 4: ...Contents January 24 2017 CLG835H...
Page 6: ...1 2 General Information January 24 2017 CLG835H...
Page 38: ...1 34 Machine Inspection Table January 24 2017 CLG835H...
Page 156: ...3 2 Power Train System January 24 2017 CLG835H...
Page 214: ...3 2 Power Train System January 24 2017 CLG835H...
Page 272: ...3 60 Testing and adjustment January 24 2017 Power Train Test CLG835H...
Page 276: ...4 4 Hydraulic System January 24 2017 CLG835H...
Page 552: ...6 2 Driver s Cab System January 24 2017 CLG835H...
Page 608: ...7 2 Structure January 24 2017 CLG835H...
Page 662: ...8 4 Electrical System January 24 2017 CLG835H...
Page 677: ...8 19 January 24 2017 Structure Function Principle CLG835H Power System P18E00014...