7-31
January 24, 2017
Removal and Installation
CLG835H
Removal and installation of work implement system
Installation of boom
Figures
Operation instruction
Tools
1) Lift the boom to mounting position
with lifting equipment, and align
boom hole with the boom mount-
ing hole on front frame.
WARNNING: Fingers cannot be
put into the hole when aligning
with the hole, otherwise it may
cause personal injury!
CAUTION: The personnel
operating lifting equipment
shall have relevant qualifications,
and only can operate on the premise
that equipment and lifting sling are
normal and safety is guaranteed!
Hoisting
equipment (over
3ton)
2) Install boom pin, and
simultaneously select the shim
with appropriate thickness
according to clearance of boom
and front frame to make sure
clearance at one side is less than
1mm/0.04in.
Sledge hammer
3) Install captive bolt
18# Wrench
P18S00048
P18S00049
P18S00050
Summary of Contents for CLG835H
Page 2: ......
Page 4: ...Contents January 24 2017 CLG835H...
Page 6: ...1 2 General Information January 24 2017 CLG835H...
Page 38: ...1 34 Machine Inspection Table January 24 2017 CLG835H...
Page 156: ...3 2 Power Train System January 24 2017 CLG835H...
Page 214: ...3 2 Power Train System January 24 2017 CLG835H...
Page 272: ...3 60 Testing and adjustment January 24 2017 Power Train Test CLG835H...
Page 276: ...4 4 Hydraulic System January 24 2017 CLG835H...
Page 552: ...6 2 Driver s Cab System January 24 2017 CLG835H...
Page 608: ...7 2 Structure January 24 2017 CLG835H...
Page 662: ...8 4 Electrical System January 24 2017 CLG835H...
Page 677: ...8 19 January 24 2017 Structure Function Principle CLG835H Power System P18E00014...