Tools
1. Remove linkage front pin
By referring to the steps for
removing linkage front pin in
removal of bucket, remove link-
age front pin.
2. Remove linkage rear pin
1) Remove captive bolt of rear
pin of linkage
18# Wrench
2) Hook the linkage by a lifting
appliance and tighten the
hanger slightly.
CAUTION: The
personnel operating
lifting equipment shall have
relevant qualifications, and
only can operate on the
premise that equipment and
lifting sling are normal and
safety is guaranteed!
Hoisting
equipment (over
1ton)
P18S00035
Summary of Contents for CLG835H
Page 2: ......
Page 4: ...Contents January 24 2017 CLG835H...
Page 6: ...1 2 General Information January 24 2017 CLG835H...
Page 38: ...1 34 Machine Inspection Table January 24 2017 CLG835H...
Page 156: ...3 2 Power Train System January 24 2017 CLG835H...
Page 214: ...3 2 Power Train System January 24 2017 CLG835H...
Page 272: ...3 60 Testing and adjustment January 24 2017 Power Train Test CLG835H...
Page 276: ...4 4 Hydraulic System January 24 2017 CLG835H...
Page 552: ...6 2 Driver s Cab System January 24 2017 CLG835H...
Page 608: ...7 2 Structure January 24 2017 CLG835H...
Page 662: ...8 4 Electrical System January 24 2017 CLG835H...
Page 677: ...8 19 January 24 2017 Structure Function Principle CLG835H Power System P18E00014...