2-10
Basic Information
January 24, 2017
Universal tool, tooling list
CLG835H
Universal tool, tooling list
Precautions on removal and installation:
1. Assembly and disassembly must be carried
out when engine is cool. In general, open
engine hood after engine is shut down, and
wait for 15 minutes before the engine is
cooled down.
2. Measurement equipment and tools such as
torque wrench, etc. shall have compliance
certificates issued by metrological depart-
ment;
3. Because many other related components on
the complete machine are concerned during
the removal and installation of each compo-
nent, removed components (especially stan-
dard parts) shall be reasonably placed to
avoid wrong installation, neglected installa-
tion, part missing, etc. during reassembly.
4. If the removal and installation of other com-
ponents on the complete machine are con-
cerned in the removal and installation of each
component, tools are referred to the tool list
for the removal and installation of other com-
ponents and not listed in the tool list of this
component;
5. If the expected effect can be reached in the
ways of using open-end wrench, blower gun
and socket as well as ratchet wrench and
socket to remove and install, anyone can be
chosen.
Name
Specification
Open-end wrench
7#, 8#,10#, 11#, 12#, 13#, 16#,
18#, 19#, 20#, 22#, 24#, 30#
Ratchet wrench,
socket
Ratchet wrench, 10#, 11#, 12#,
13#, 16#, 18#, 19#, 20#, 22#, 24#
and 30# socket
Torque wrench
120±6N.m(12±0.6kgf.m),
1020±6N.m(102±0.6kgf.m)
Traveling crane
More than 2t (4410Ib)
Wire rope with
hooks
Weight load over 840Kg
(1852.2Kg)
Steel ruler
Steel ruler
Straight screw-
driver
Cross screwdriver
T25
Lifting eye
Plastic sealing
membrane
Waste oil tank
Remarks:
Summary of Contents for CLG835H
Page 2: ......
Page 4: ...Contents January 24 2017 CLG835H...
Page 6: ...1 2 General Information January 24 2017 CLG835H...
Page 38: ...1 34 Machine Inspection Table January 24 2017 CLG835H...
Page 156: ...3 2 Power Train System January 24 2017 CLG835H...
Page 214: ...3 2 Power Train System January 24 2017 CLG835H...
Page 272: ...3 60 Testing and adjustment January 24 2017 Power Train Test CLG835H...
Page 276: ...4 4 Hydraulic System January 24 2017 CLG835H...
Page 552: ...6 2 Driver s Cab System January 24 2017 CLG835H...
Page 608: ...7 2 Structure January 24 2017 CLG835H...
Page 662: ...8 4 Electrical System January 24 2017 CLG835H...
Page 677: ...8 19 January 24 2017 Structure Function Principle CLG835H Power System P18E00014...