Working range
Dimension A [mm]
X = 1250
X = 2000
X = 3000
X = 4000
Dimension B [mm]
5020
5770
6830
8530
Total length of transport unit for basic machine
The basic machine can be transported to the installation site using
a gantry crane, crane truck, or armored rollers. The basic machine
and units are first positioned next to the actual installation site.
Danger
The center of gravity of the transport unit for the basic
machine is close to the front edge of the machine body!
The machine body can tip over if not transported properly.
This could lead to severe bodily injury or even death as well
as substantial damage to property.
½
Rotational moving device, position 4, fig. 32509 must fit closely
to stop, position C.
½
During transport, no persons are allowed in the danger zone.
For transport on armored rollers:
1.
Position hydraulic hoisting jacks at the front and rear of the
machine body. Raise all four hydraulic hoisting jacks
simultaneously. Lift hydraulic hoisting jack evenly.
2.
Arrange the armored rollers, positions 5 and 6, and the
rotational moving device, position 4, under the machine body
as shown in figure 32509.
3.
Lower hydraulic hoisting jacks simultaneously.
4.
Slowly move machine body to the installation site.
For transport using gantry crane or crane truck:
1.
Attach the cross beam to the swivel bearers, positions 1 and 2
(4x), figure 32509 on the machine body in such a way that the
chains hang vertically and are arranged symmetrically.
2.
Move the basic machine to the installation site using a crane
truck or gantry crane.
Table 2-27
Transporting basic machine
to installation site
Содержание LASERCELL 1005
Страница 1: ...Operator s manual TRUMPF LASERCELL 1005...
Страница 2: ......
Страница 3: ...Operator s manual TRUMPF LASERCELL 1005 Edition 07 2004...
Страница 6: ...0 6 Before You proceed B337EN00 DOC...
Страница 22: ...0 22 Table of Contents B337EN00 DOC...
Страница 23: ...1...
Страница 61: ...1 38 Laser processing B337EN01 DOC...
Страница 62: ...2...
Страница 107: ...3...
Страница 160: ...4...
Страница 238: ...4 78 Operation B337EN4_3 Fig 39422 Fig 39423en Cutting a large contour Cutting a medium contour...
Страница 408: ...4 248 Operation B337EN4_8 Fig 36634 Fig 36630 4 Select Backup to ZIP press 4 5 Press Enter...
Страница 409: ...B337EN4_8 Operation 4 249 Fig 36626 Fig 36627 Backup starts 6 Enter file name press Enter 7 Press Y...
Страница 412: ...4 252 Operation B337EN4_8...
Страница 413: ...5...
Страница 515: ...5 102 Further service programs B337EN05 DOC...
Страница 516: ...6...
Страница 546: ...6 30 Machine maintenance B337EN06 doc 5 Maintenance of pneumatic components and filters 5 1 Instrument panel Fig 39484...
Страница 589: ...7...
Страница 628: ...8...
Страница 635: ...B337EN08 DOC Cross hairs to cut out 8 7 5 Cross hairs to cut out Cross hairs to cut out Fig 6310...
Страница 636: ...8 8 Cross hairs to cut out B337EN08 DOC...
Страница 637: ...9...
Страница 643: ...9 6 Diagram Location of measuring points B337EN09 DOC...
Страница 644: ...10...