MAC215990
427
Revision A
1001322
A
B
Figure 4.358: U-Joint
4.
Remove four bolts (A) securing the reel tube to U-joint
flange (B), and move the reel sideways.
1001325
A
B
C
Figure 4.359: U-Joint
5.
Remove six bolts (A) attaching U-joint flange (B) to driven
sprocket (C).
6.
Remove the U-joint.
NOTE:
It may be necessary to move the right reel sideways so that
the U-joint can clear the tube.
Installing Double-Reel U-Joint
Once the old U-joint has been removed, the new one can be installed.
1001325
A
B
C
Figure 4.360: U-Joint
1.
Position U-joint flange (B) onto driven sprocket (C)
as shown.
2.
Apply medium-strength threadlocker (Loctite® 243 or
equivalent), and install six bolts (A). Hand-tighten the bolts;
do
NOT
torque the bolts.
NOTE:
Only four bolts (A) are shown in the illustration at right.
NOTE:
It may be necessary to move the right reel sideways so that
the U-joint can clear the reel tube.