Commissioning
5.3 Procedure for commissioning via STARTER
Drive converter cabinet units
Operating Instructions, 07/07, A5E00288214A
123
Figure 5-7
Setting the interface - properties
NOTICE
You must activate PG/PC is the only master on bus if no other master (PC, S7, etc.) is
available on the bus.
Note
Projects can be created and PROFIBUS addresses for the drive objects assigned even if a
PROFIBUS interface has not been installed on the PC.
To prevent bus addresses from being assigned more than once, only the bus addresses
available in the project are proposed.
6. Once you have done this, click OK to confirm the settings and return to the project Wizard.