Stage
Precautions
Ensure that the crane is properly located and avoid long-
distance hoisting.
Keep the unit stable and horizontal during hoisting, and
ensure that the diagonal gradient of the unit is within 5
degrees.
Lift and land the unit slowly to prevent shock to devices
inside it.
Remove the steel ropes after ensuring that the unit is
placed evenly on the concrete platforms.
Tools: marker, ink fountain, long leather measuring tape, crane, socket wrench,
torque wrench, Phillips screwdriver, jack, steel hoisting rope, level, level gauge,
hammer drill, angle ruler, claw hammer, vacuum cleaner
Materials: unit to be hoisted, expansion bolt, angle steel bracket
Procedure
Step 1 Prepare concrete platforms.
Figure 4-3 Concrete platforms for a single unit (unit: mm)
FusionCol8000-E240 Modular Indirect Evaporative
Cooling System
User Manual
4 System Installation (Building Scenario)
Issue 03 (2021-04-20) Copyright © Huawei Digital Power Technologies Co., Ltd.
41