Figure 4-4 Concrete platforms for combined units (unit: mm)
(1) FusionCol8000-E
(2) Concrete platform
Step 2 Determine the reference points for installing a unit on the concrete platforms.
Mark the reference points using a marker.
Step 3 Mark the mounting positions for the four corner fittings of the unit using an ink
fountain and long measuring tape.
NO TICE
When marking the mounting positions for corner fittings, ensure that the four
lines form a rectangle.
Step 4 Place the shock absorption pads at the corresponding positions of corner fittings
on the concrete platforms.
Step 5 Adjust the unit in the required direction, connect the steel hoisting ropes, and
hoist the unit onto the concrete platforms.
NO TICE
When hoisting the unit, ensure that the four corner fittings of the unit are aligned
with the marked mounting positions for corner fittings on the concrete platforms.
FusionCol8000-E240 Modular Indirect Evaporative
Cooling System
User Manual
4 System Installation (Building Scenario)
Issue 03 (2021-04-20) Copyright © Huawei Digital Power Technologies Co., Ltd.
42