Chapter 3 Site Planning and Preparation
Installation and Commissioning Manual
87
F
S
P
3000R
7 R
11
.1 8000
0015930
Issue
B
, ©
2012
ADVA AG Optical Netw
orking
ADVA Conf
idential
30
Does each separate power source have a circuit
breaker at the power distribution point?
31
Has a PDU or an AC/DC rectifier per rack been
installed and has it been tested for proper voltage?
32
Are the AC power receptacles of a three-conductor
grounding type and located within a reasonable
distance?
Cable and Cabling Requirements
33
Are all required DC power cables of the correct type,
lengths and quantity available?
34
Are the required AC power cables of the correct type
and quantity available?
35
Are all power cable pairs labeled?
36
Has cable routing been determined and performed?
37
Are all required network cables of the correct types
available?
38
Are all required fiber-optic jumpers available and
clearly labeled as TX (transmit) and RX (receive)?
39
Are all fiber-optic interface patch cables of the correct
type?
40
Have all fiber-optic interface patch cables been
installed, routed and clearly labeled?
41
Have client and network lines been tested and shown
not to exceed the optical budget?
Other Requirements
42
Have personnel been appointed for installation and
testing?
43
Has pilot online testing been formulated?
I have performed each of the above checks and the location is ready for installation in accordance
with the above items.
Printed Name:
Signature and Date:
Table 20: Site Survey Checklist (Continued)