Site Preparation
86
Installation and Commissioning Manual
F
S
P
3000R
7 R
11
.1 8000
0015930
Issue
B
, ©
2012
ADVA AG Optical Netw
orking
ADVA Conf
idential
12
Has a cable management kit been installed at the front
of each equipment rack?
13
Is there an ESD connection socket or an unpainted
earth point on each rack for connecting personal
grounding devices?
14
Has each rack correctly been leveled and secured to
the floor?
15
Has each rack been secured to the ceiling, if required?
16
Has each rack been earthed by a Protective Earthing
Conductor according to local policies?
17
Has each rack been numbered and labeled?
18
Which type of rack has been installed?
19-inch cabinet
19 inch
ETSI
NEBS
Environmental and Ventilation Requirements
19
Does the installation location meet operating
temperature and relative humidity specifications?
20
Is the capacity of the air conditioning system sufficient
for all the equipment installed in the installation
location?
21
Is there sufficient ventilation when placing multiple
shelves in a cabinet?
22
Does each shelf have an acceptable clearance to
allow cooling air to be exhaust on both sides?
Clearance Requirements
23
Is there enough clearance (for example, through
entrances and doorways) to move the equipment
between the loading dock or receiving department and
the location where it is to be installed?
24
Does each rack have adequate service and access
clearances?
25
Is there enough clearance to access shelf components
for cabling and maintenance?
26
Is there enough clearance space between the rack
and a wall or the next line-up to perform any
necessary work?
Power Source Requirements
27
Have the requirements of the local and national
electrical codes been met?
28
Has local input power been tested and confirmed to be
within budget?
29
Does each shelf have two independent power
sources, if redundancy is required?
Table 20: Site Survey Checklist (Continued)