1.
Gather pre-installation information.
2.
Upon arrival on customer site, introduce yourself and find out the responsi-
bilities of the customer contact men.
3.
Describe installation procedures to customer and required assistance.
4.
Enquire customer safety policy, describe our safety policy and ensure
customer participation.
5.
Contact through customer, side contractors (e.g. refrigeration contractors)
and clarify delivery limitations and agree on time schedules.
6.
Install equipment according to separate check list.
7.
Report any errors on Deviation Reports.
8.
Fill in “Actual installation hours”.
9.
Send the Electrical System form to confirm changes/no changes of the
Electrical System.
10.
Test run the equipment and test all functions.
11.
Perform belt tension test (if applicable).
12.
Describe Start up procedure to customer and ensure his participation.
13.
Test run in production temperature.
14.
Hand over manual book.
15.
Train operating personnel in starting and stopping the equipment.
16.
Train cleaning personnel in cleaning the equipment.
17.
Train maintenance personnel in periodic maintenance checks.
18.
Test run with products.
19.
Meet customer contact person to explain the work carried out, remaining
work (if any) and ensure that customer can operate the equipment. Re-
quest the customer to sign the “Take over certificate”.
20.
Remove drawings and site-supervisors log-book from site.
21.
The Control Project Manger ensures that all reports are delivered and filed
on the FSSD Europe Intranet.
Содержание FoodTech Frigoscandia GYRoCOMPACT M7
Страница 1: ...0 INSTALLATION MANUAL Frigoscandia GYRoCOMPACT M7 Spiral Freezer...
Страница 2: ...N...
Страница 4: ...INSTALLATION 2 2 INTRODUCTION 02 INSTALLATION MANUAL...
Страница 6: ...2 2 0000 07 01 01 00 INSTALLATION MANUAL INSTALLATION...
Страница 8: ...2 2 0000 07 01 02 00 INSTALLATION MANUAL INSTALLATION...
Страница 16: ...10 0000 00 01GB 11 24 SAFETY...
Страница 20: ...SAFETY 4 1000 07 01GB 02 03...
Страница 34: ...6 INSTALLATION PREPARATIONS 1000 07 01GB 05 03...
Страница 42: ...8 DELIVERY INFORMATION 0000 03 01GB 11 09...
Страница 44: ...2 INSTALLATION 1000 07 01GB 07 01 INSTALLATION MANUAL...
Страница 48: ...2 INSTALLATION 1000 07 01GB 09 03 INSTALLATION MANUAL...
Страница 54: ...2 INSTALLATION 1000 07 01GB 12 00 INSTALLATION MANUAL...
Страница 58: ...4 INSTALLATION 1000 07 01GB 13 01 INSTALLATION MANUAL...
Страница 62: ...2 INSTALLATION 1000 07 01GB 15 00 INSTALLATION MANUAL...
Страница 70: ...2 INSTALLATION INSTALLATION MANUAL 1000 07 01GB 18 01...
Страница 72: ...2 INSTALLATION 1000 07 01GB 20 00 INSTALLATION MANUAL...
Страница 78: ...6 INSTALLATION 1000 07 01GB 22 03 INSTALLATION MANUAL...
Страница 90: ...4 INSTALLATION 1000 07 01GB 29 00 INSTALLATION MANUAL...
Страница 110: ...6 INSTALLATION 1000 07 01GB 25 01 INSTALLATION MANUAL...
Страница 128: ...18 INSTALLATION 1000 07 01GB 26 06...
Страница 144: ...2 INSTALLATION 1000 07 01GB 19 00 INSTALLATION MANUAL...
Страница 152: ...2 INSTALLATION 1000 07 01GB 36 00 INSTALLATION MANUAL...
Страница 188: ...SERVICE INFORMATION SERVICE INFO NUMBER 127 EQUIPMENT GENERAL REVISED BY LAR REVISION DATE MAY 2012 14 127 01GB 04...
Страница 194: ...10 221 01GB 03 SERVICE INFO...
Страница 200: ...10 171 01GB 02 SERVICE INFO...
Страница 222: ...172 347 01GB 00 SERVICE INFO...
Страница 230: ...10 039 01GB 03 SERVICE INFORMATION...
Страница 256: ...172 CORRECTIVEMAINTENANCE 1000 06 01GB 10 11...
Страница 269: ...Automatic Pump Station PZC M1 PZE M2 CIP M3 Directions for use 3 19 EN...
Страница 277: ...9 ALTO Danmark A S...
Страница 288: ...2004 All rights reserved ALTO Danmark A S Blyt kkervej 2 DK 9100 Aalborg No 0617563C May 2004 Printed in Denmark...