Installing the Cyclone
(optional) (continued)
4
Bolt the cyclone bracket to the CH Hopper, using the hardware removed
in Steps 2 and 3.
Do not fully tighten the bolts, the cyclone installation may
need to be adjusted for hard piping of the cyclone’s inlet and outlet ports.
5
Using a forklift, hoist or crane, raise the cyclone body to its installation
location on the bracket mounted to the CH Hopper.
Installation location
depends upon your system setup.
6
Mount the cyclone body to its installation location on the bracket using the
supplied hardware.
Do not tighten the bolts, the cyclone installation may need
to be adjusted for hard piping of the cyclone’s inlet and outlet ports.
7
Locate the three (3) 90 degree pieces of tubing.
These pieces will connect
the CH Hopper to the cyclone.
8
Bolt two (2) of the pieces of 90 degree tubing together using the supplied
hardware.
Be sure to place the supplied gasket between the two (2) pieces of
tubing before tightening the tube bolts. One of the pieces includes the dew point
return port; the port should be located on the same end as the connection of the
two (2) pieces of 90 degree tubing.
CAUTION:
To prevent accident
and injury, move the cyclone
separator to its mounting loca-
tion using a forklift, hoist or
crane.
3-18
l I n s t a l l a t i o n - G e n e r a l
(continued)
Bolts (4)
(Two (2) for each
side)
Summary of Contents for HTC 120
Page 10: ...viii l Table of Contents ...
Page 30: ...2 14 l Description ...
Page 35: ...Installation General Installation General l 3 5 3 I n s t a l l a t i o n ...
Page 65: ...Installation Hard Piping Kits Installation Piping Hoses l 3 35 3 I n s t a l l a t i o n ...
Page 80: ...3 50 l Installation Piping Hoses ...
Page 88: ...3 58 l Installation Piping Hoses ...
Page 92: ...3 62 l Installation Conveying Lines ...
Page 93: ...Installation Water Lines 3 I n s t a l l a t i o n Installation Water Lines l 3 63 ...
Page 124: ...3 94 l Installation Gas Piping and Exhaust Flue ...
Page 125: ...Installation Testing 3 I n s t a l l a t i o n Installation Testing l 3 95 ...
Page 250: ...4 108 l Operation ...
Page 286: ...5 36 l Maintenance ...