3-112
l I n s t a l l a t i o n - Te s t i n g
Testing the Installation
4
From the System Control Screen (Screen 16), press the “Start System”
button.
If everything is installed correctly:
•
The regeneration and process blowers turn on. If process blower does
not turn on, verify that the VFD is set to “Remote
•
The regeneration heater turns on.
•
The process heater will energize (HTC or GasTrac)
•
The dryer’s desiccant wheel starts turning. If the desiccant wheel does
not turn, verify that the desiccant wheel tie has been removed.
•
The loader and pump will come on (if supplied, and if loaders enabled).
5
From the System Control Screen (Screen 16), press the “Stop System”
button.
If everything is installed correctly:
•
The blowers will process and continue running as needed to cool the
heaters. (until regeneration heaters are less than 150°F{66°C})
6
The test is over.
If the dryer performed the normal operating sequences as
outlined, reconnect the material source to the optional hopper receiver and begin
normal operation. If it did not, refer to the
Troubleshooting section
of the User
Guide.
Summary of Contents for HTC 120
Page 10: ...viii l Table of Contents ...
Page 30: ...2 14 l Description ...
Page 35: ...Installation General Installation General l 3 5 3 I n s t a l l a t i o n ...
Page 65: ...Installation Hard Piping Kits Installation Piping Hoses l 3 35 3 I n s t a l l a t i o n ...
Page 80: ...3 50 l Installation Piping Hoses ...
Page 88: ...3 58 l Installation Piping Hoses ...
Page 92: ...3 62 l Installation Conveying Lines ...
Page 93: ...Installation Water Lines 3 I n s t a l l a t i o n Installation Water Lines l 3 63 ...
Page 124: ...3 94 l Installation Gas Piping and Exhaust Flue ...
Page 125: ...Installation Testing 3 I n s t a l l a t i o n Installation Testing l 3 95 ...
Page 250: ...4 108 l Operation ...
Page 286: ...5 36 l Maintenance ...