Periodic Maintenance
UVTOCMaintenance.fm
Section 7
7.3 Periodic Maintenance
The manufacturer is not responsible
for damage caused by the failure of
the user to follow the recommended
periodic maintenance.
Perform the following routine preventive maintenance on the recommended
schedule to ensure satisfactory long-term performance.
Important Note: The analyzer circuit board components are sensitive
to static electricity damage in a powered or unpowered state. Do not touch
circuit boards or their components without wearing a properly grounded
wrist strap. See
Electrostatic Discharge (ESD) Considerations
.
7.4 Shut Down
Important Note: The shutdown procedure must be strictly followed to avoid damage to
the analyzer on subsequent startup.
The analyzer should run continuously, if possible. Turning the lamps on and
off unnecessarily will shorten their life. If it is necessary to turn the lamps off,
observe the following cautions:
•
Do not allow the UV lamps to remain lit without liquid flowing
through the reactor because plugging and/or damage to the reactor
may result.
•
If measurement is not necessary or possible, substitute DI water for
sample in the analyzer.
Table 14 Maintenance Tasks and Schedule
Maintenance Task
Daily
Monthly
Quarterly
Annually
Check for alarms.
X
X
X
X
Check for liquid leaks and other unusual conditions. Eliminate leaks
immediately to avoid analyzer damage.
X
X
X
X
Check the flowmeter reading for the reactor carrier flow. It should be
stable and near the reading shown when the analyzer was
commissioned.
X
X
X
X
Visually observe that the sparge gas bubbles are flowing correctly in
the GLS and sparger.
Note: The sparger on the TC version is bypassed with the conversion.
X
X
X
X
Prepare reagents and refill containers.
X
X
X
Recalibrate the analyzer, using fresh carbon standards.
X
X
X
Check the pressure of the carrier gas feed to ensure that an adequate
supply is available.
X
X
X
If the analyzer is obviously dirty, perform a cleaning.
X
X
X
Replace all peristaltic pump tubing. See
.
X
X
Remove the UV lamps and remove the aluminum foil from the lamps to
perform lamp inspection. The lamp surface should be clear. If it is not,
run cleaning solution through the analyzer. Before returning to on-line
operation, wrap standard aluminum foil around each lamp to prevent
UV exposure.
X
Clean the IR sample cell and windows with a suitable solvent.
X
Содержание 1950Plus
Страница 2: ...Page 2 4195M0040title page fm...
Страница 12: ...Page 12 Safety Precautions UVTOCSafety Precautions fm...
Страница 24: ...Page 24 EPA Mode UVTOCIntroduction fm...
Страница 26: ...Page 26 Installation UVTOCInstallation Stopper fm...
Страница 28: ...Page 28 Unpacking and Installation UVTOCUnpacking Installation Setup fm Section 2 Figure 6 Analyzer Dimensions...
Страница 54: ...Page 54 Storage and Handling Tips UVTOCReagents and Standards fm...
Страница 60: ...Page 60 Analyzer Adjustments UVTOCCommissioning fm...
Страница 62: ...Page 62 Operation UVTOCOperation Stopper fm...
Страница 110: ...Page 110 Maintenance UVTOCMaintenance Stopper fm...
Страница 128: ...Page 128 Replacing the Fuses UVTOCMaintenance fm...
Страница 137: ...Section 8 Page 137 UVTOCTroubleshooting and Service fm Service Menu Structure 8 5 Service Menu Structure...
Страница 146: ...Page 146 Fault ID Codes UVTOCTroubleshooting and Service fm...
Страница 152: ...Page 152 TC Conversion UVTOC_TC_conversion fm...
Страница 160: ...Page 160 Analyzer Pump Configurations UVTOC_PumpConfiguration fm...
Страница 164: ...Page 164 Glossary UVTOCGlossary fm...
Страница 172: ...Page 172 Replacement Parts UVTOCReplacement Parts fm...
Страница 176: ...Page 176 General Information UVTOCGeneral Information Stopper fm...
Страница 182: ...Page 182 4195M0040Certification fm Certification...