KW Aufzugstechnik GmbH OPERATING MANUAL DAVID-613
DAVID-D613-V125-E 13.04.2021
Page - 241 -
I05- Commissioning with
CANopen
Shaft-Copy
ELGO-SAFE 33CP
1.0 Making the mechanical / electrical Installation
The ELGO LIMAX CP33 is an absolute measuring system for determining the position of the elevator car, consisting of
the reading head, the steel belt and the fixing set.
The measuring system can work at a shaft height of up to 100m and a maximum speed of 4.0 m / s with a millimeter
resolution. The magnetic tape is fixed with shaft tab holders in the upper and lower part of the shaft. Above the below
shaft flag holder a shaft flag holder is attached to the belt breaker.
It is important to pay attention to the correct spring preload.
Passed through a gap in the reader on the magnetic tape
Please also note the ELGO-LIMAX installation instructions!
Montage-Set
Assembly kit complete:
0 Reader with mounting bracket
1 2x Shaft flag holder for top & bottom
2 1x Shaft flag holder for
tape demolition switch
3 Bandolder below for tape demolition
switch
4 Top band holder
5 Tension spring
6 2x cable ties
7 6x screws, u-washer, nuts &
Clamping claws
8 Tape breaker with cable and attachment
9 Magnetic tape
1
.
Mount the shaft flag holder
1
in the shaft head in compli-
ance with the
legal and company-related safety regula-
tions
. With fastening set
4
(clamps) with a tightening torque
of 20 Nm.
2.
Attach the top end of the tape by inserting the holder
4
into
the shaft flag holder
1
. Before inserting the magnetic tape,
please check the orientation of the tape.
The printed arrows
on the magnetic tape must point to the shaft head
!
The image to the right shows you how to insert the tape into
the holder. Finally, the band end is secured with a cable tie
6
.
3.
Go down with inspection and unwind the tape directly.
Please wear the personal protective equipment recom-
mended for use. Avoid damage to the tape.
4.
Drive the cabin into the middle of the shaft and let the en-
tire belt into the shaft pit so that it hangs freely.
Содержание DAVID 613
Страница 1: ...OPERATING MANUAL LIFT CONTROLLER SYSTEM DAVID 613 FUNCTIONS START UP INSTRUCTIONS...
Страница 2: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 2...
Страница 7: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 7 8 INDEX 263...
Страница 10: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 10...
Страница 12: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 12...
Страница 13: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 13...
Страница 14: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 14...
Страница 34: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 34...
Страница 35: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 35...
Страница 98: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 98...
Страница 124: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 124 Unit shaft copying system...