KW Aufzugstechnik GmbH OPERATING MANUAL DAVID-613
DAVID-D613-V125-E 13.04.2021
Page - 230 -
I04- Commissioning with
CANopen
Shaft-Copy ANTS-SAFE
1.0 Making the mechanical / electrical installation
1 Assembly of the Variotech-ANTS System
The Variotech ANTS is an absolute measuring system for determining
the position of the elevator car, consisting of the reading head, the steel
band and the mounting set.
The steel strip is fixed in the upper and lower part of the shaft by means
of shaft flag holders. Pay attention to the correct spring preload.
The reader can be placed on the steel strip by means of a lateral opening.
The position of the large & small holes in the steel strip must be observed
when inserting!
Please also note the Variotech ANTS installation instructions!
Mounting kit complete:
1 Shaft holder straight and
angled
2 Screws & Clamps
3 Tension spring mounting at the bottom
4 K-hook tape mounting on top
5 Steel tape
6 Holder for reader-unit with attachment
7 Reader-unit with cable & plug
8 Stainless Steel Band
1. Mount the shaft flag holder in the shaft head in compliance with legal
and company-related safety regulations. Depending on whether you are
installing a central rail or backsack system, use the shaft flag holder
straight or angled and fasten it with the fastening set 2.
2. Attach the upper end of the belt by inserting the carabiner hook 4 into
the shaft flag holder 1. Before doing this, please check the orientation of
the tape using the large & small holes!
3. Drive down with the inspection and rewind the tape directly. Please
provide personal protective equipment recommended for use.
4. Further assembly takes place in the shaft pit. Before entering the pit,
ensure that the car is secured against uncontrolled downward move-
ment. For work longer than 15 minutes, the car must be supported in
compliance with the safety regulations of the assembly company!
5. Equivalent to steps 1 and 2, the lower shaft flag holder 1 and the
holder 2 for the magnetic tape are to be mounted. A tension spring 3 is
to be installed and it must be saved with a stainless steel band! Deci-
sive for the functionality is the spring preload.
It should be 170mm!
Содержание DAVID 613
Страница 1: ...OPERATING MANUAL LIFT CONTROLLER SYSTEM DAVID 613 FUNCTIONS START UP INSTRUCTIONS...
Страница 2: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 2...
Страница 7: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 7 8 INDEX 263...
Страница 10: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 10...
Страница 12: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 12...
Страница 13: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 13...
Страница 14: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 14...
Страница 34: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 34...
Страница 35: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 35...
Страница 98: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 98...
Страница 124: ...KW Aufzugstechnik GmbH OPERATING MANUAL DAVID 613 DAVID D613 V125 E 13 04 2021 Page 124 Unit shaft copying system...