13.3.5
HP fuel pipe (fuel pump to fuel rail) - grind the sealing face
Periodicity
Description
Unscheduled
Duration for performing preliminary requirements
0.0 man-hours
Duration for performing the procedure
0.5 man-hours
Duration for performing the requirements after job completion
0.0 man-hours
Personnel
Description
Specialization
QTY
Engine crew
Basic
AR
Support equipment
Description
Part No.
CSN
QTY
grinding tool
94870F
1
template
94870H
1
sleeve
94870E
1
locknut
94870G
1
electric drill
N/A
1
Supplies
Description
QTY
emery cloth (30 to 80 CAMI)
A/R
emery cloth (100 to 600 CAMI)
A/R
Spare Parts
Description
Part No.
CSN
QTY
None
SAFETY PRECAUTIONS
•
None
PRELIMINARY OPERATIONS
•
The applicable HP fuel pipe must be removed, refer to
13.3.4 HP fuel pipe (fuel pump to
X82-B
AA00-8752-01AAA-655A-A
Maintenance Manual
HP fuel pipe (fuel pump to fuel rail) - grind the sealing face
Winterthur Gas & Diesel Ltd.
- 740 -
Issue 001 2020-10
Summary of Contents for X82-B
Page 825: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 1 9...
Page 826: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 2 9...
Page 827: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 3 9...
Page 828: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 4 9...
Page 829: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 5 9...
Page 830: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 6 9...
Page 831: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 7 9...
Page 832: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 8 9...
Page 833: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 9 9...