PROCEDURE
1
If it necessary to move the connecting rod away from the area, do
:
1.1
Read the applicable safety precautions.
1.2
Put on the applicable personal protective equipment.
1.3
1.4
Attach the spur-geared chain block (002, 006) to the connecting rod (003) and
the engine room crane.
1.5
Operate the engine room crane to lift and move the connecting rod to the
applicable area.
1.6
Lower the connecting rod (003) on to the floor.
1.7
Remove the engine room crane from the chain blocks (002, 006)
1.8
Attach the two chain blocks (002 and 006) to the top platform and the shackles
(005).
1.9
Lift the connecting rod (003) a small distance.
1.10
Attach two more shackles (009) to the top platform.
1.11
Attach two more chain blocks (007, 008) to the connecting rod (003) and
shackles (009) as shown in step B.
1.12
Attach and remove the chain blocks (002, 006, 007, 008) and shackles (005,
009) as given in
to continue to move the connecting rod to the
applicable position for installation (step C).
1.13
Lower the connecting rod (003) on to the floor.
1.14
Remove the chain blocks and the shackles.
1.15
Continue the installation procedure from
X82-B
AA00-3303-00AAA-720A-A
Maintenance Manual
Connecting rod - install
Winterthur Gas & Diesel Ltd.
- 379 -
Issue 001 2020-10
Summary of Contents for X82-B
Page 825: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 1 9...
Page 826: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 2 9...
Page 827: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 3 9...
Page 828: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 4 9...
Page 829: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 5 9...
Page 830: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 6 9...
Page 831: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 7 9...
Page 832: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 8 9...
Page 833: ...Approved TIGHTENING INSTRUCTIONS Rev B Page 9 9...