7. Disconnect customer electrical load from PowerGen prior to enabling the PowerGen for the
first time.
8. Start the PowerGen by clicking
Enable
in Qnergy Lynx.
Figure 12-17 FPC Tab, Enable
If the PowerGen does not start (ignition failure fault): Adjust the #3 screw (shown in Figure
12-13 on page 84) counter-clockwise a half a turn to start with a richer combustion. This can be
repeated up to six times. If unit still does not ignite, contact Qnergy customer support, (801)
413-7668.
9.Under the QEC/Config Tab Set
Minimum Engine Power to 5000W
, Click Set,
while the
PowerGen is running
.
WARNING:
Disconnect customer electrical load
prior to enabling the PowerGen for the first time
and while setting-up QEC Load-following
parameters.
Contact Qnergy Customer Support if unfamiliar
about how to correctly setup the PowerGen,
Qnergy Lynx, Load-following parameters:
+1(801)413-7668
(Customer Support Hotline).
Summary of Contents for PowerGen 5650 Series
Page 1: ...7045 102089 000 June 1 2021 Installation Operation Manual FOR A QUALIFIED INSTALLER...
Page 8: ...iv...
Page 12: ...iv Figure 21 9 ATS Enclosure 179 Figure 21 10 Battery Connection Schematic 181...
Page 28: ...SYSTEM INTRODUCTION 16 Figure 3 6 P ID Diagram...
Page 69: ...QNERGY LYNX SOFTWARE 57 Figure 6 57 FPC FEB QEC Firmware Update...
Page 158: ...MAINTENANCE 146 Figure 17 2 Radiator and Over Flow Tank...
Page 194: ...POWERGEN OPTIONAL FEATURE SETS 182...