8-1
7SA6 Manual
C53000-G1176-C156-2
Installation and Commissioning
8
This chapter is primarily for personnel who are experienced in installing, testing, and
commissioning protective and control systems, and are familiar with applicable safety
rules, safety regulations, and the operation of the power system.
Installation of the 7SA6 is described in this chapter. Hardware modifications that might
be needed in certain cases are explained. Connection verifications required before the
device is put in service are also given. Commissioning tests are provided. Some of the
tests require the protected object (line, transformer, etc.) to carry load.
8.1
Mounting and Connections
8-2
8.2
Checking the Connections
8-41
8.3
Commissioning
8-47
8.4
Final Preparation of the Device
8-77
Содержание siprotec 7SA6
Страница 2: ...Siemens Aktiengesellschaft Book No C53000 G1176 C156 2 ...
Страница 18: ...xviii 7SA6 Manual C53000 G1176 C156 2 ...
Страница 32: ...Introduction 1 14 7SA6 Manual C53000 G1176 C156 2 ...
Страница 82: ...Hardware and Connections 2 50 7SA6 Manual C53000 G1176 C156 2 ...
Страница 119: ...SIPROTEC 4 Devices 4 25 7SA6 Manual C53000 G1176 C156 2 Figure 4 20 CFC Logic example ...
Страница 190: ...Configuration 5 62 7SA6 Manual C53000 G1176 C156 2 ...
Страница 559: ...Control During Operation 7 45 7SA6 Manual C53000 G1176 C156 2 Figure 7 45 Circuit breaker trip test in DIGSI 4 ...
Страница 652: ...Installation and Commissioning 8 78 7SA6 Manual C53000 G1176 C156 2 ...
Страница 724: ...Technical Data 10 56 7SA6 Manual C53000 G1176 C156 ...
Страница 800: ...Appendix A 76 7SA6 Manual C53000 G1176 C156 2 ...
Страница 866: ...Appendix B 66 7SA6 Manual C53000 G1176 C156 2 ...