3-42
C70 Capacitor Bank Protection and Control System
GE Multilin
3.4 MANAGED ETHERNET SWITCH MODULES
3 HARDWARE
3
3.4.5 UPLOADING C70 SWITCH MODULE FIRMWARE
a) DESCRIPTION
This section describes the process for upgrading firmware on a UR-2S or UR-2T switch module.
There are several ways of updating firmware on a switch module:
•
Using the EnerVista UR Setup software.
•
Serially using the C70 switch module console port.
•
Using FTP or TFTP through the C70 switch module console port.
It is highly recommended to use the EnerVista UR Setup software to upgrade firmware on a C70 switch module.
Firmware upgrades using the serial port, TFTP, and FTP are described in detail in the switch module manual.
b) SELECTING THE PROPER SWITCH FIRMWARE VERSION
The latest switch module firmware is available as a download from the GE Multilin web site. Use the following procedure to
determine the version of firmware currently installed on your switch
1.
Log into the switch using the EnerVista web interface.
The default switch login ID is “manager” and the default password is “manager”.
The firmware version installed on the switch will appear on the lower left corner of the screen.
2.
Using the EnerVista UR Setup program, select the
Settings > Product Setup > Communications > Ethernet Switch
> Firmware Upload
menu item.
NOTE
NOTE
Version: 2.1 beta
842869A1.CDR
Содержание UR Series C70
Страница 2: ......
Страница 10: ...x C70 Capacitor Bank Protection and Control System GE Multilin TABLE OF CONTENTS ...
Страница 30: ...1 20 C70 Capacitor Bank Protection and Control System GE Multilin 1 5 USING THE RELAY 1 GETTING STARTED 1 ...
Страница 124: ...4 30 C70 Capacitor Bank Protection and Control System GE Multilin 4 3 FACEPLATE INTERFACE 4 HUMAN INTERFACES 4 ...
Страница 344: ...5 220 C70 Capacitor Bank Protection and Control System GE Multilin 5 10 TESTING 5 SETTINGS 5 ...
Страница 396: ...8 18 C70 Capacitor Bank Protection and Control System GE Multilin 8 3 ENERVISTA SECURITY MANAGEMENT SYSTEM 8 SECURITY 8 ...
Страница 414: ...9 18 C70 Capacitor Bank Protection and Control System GE Multilin 9 1 OVERVIEW 9 THEORY OF OPERATION 9 ...
Страница 436: ...10 22 C70 Capacitor Bank Protection and Control System GE Multilin 10 4 SETTING EXAMPLE 10 APPLICATION OF SETTINGS 10 ...
Страница 547: ...GE Multilin C70 Capacitor Bank Protection and Control System B 79 APPENDIX B B 4 MEMORY MAPPING B ...
Страница 548: ...B 80 C70 Capacitor Bank Protection and Control System GE Multilin B 4 MEMORY MAPPING APPENDIXB B ...
Страница 586: ...D 10 C70 Capacitor Bank Protection and Control System GE Multilin D 1 OVERVIEW APPENDIXD D ...
Страница 598: ...E 12 C70 Capacitor Bank Protection and Control System GE Multilin E 2 DNP POINT LISTS APPENDIXE E ...