Revision A
Figure 7.23: Float Indicator Box
4.
Loosen jam nuts (A) securing float indicator cable (B) to
both sides of the float indicator bottom support, and
then disconnect the cable from the support.
5.
Float indicator cable (B) is routed around three
pulleys (C) in the float indicator box. Remove the cable
and discard.
NOTE:
Pulleys are hidden by other parts in the illustration.
Their approximate location is identified.
6.
Examine the new float indicator cable (MD #187658). You will see that it is divided into sections. The longer
covered section (A) should be installed on the left side of the float module, the middle uncovered section (B)
should be installed in the float indicator box, and the shorter covered section (C) should be installed on the right
side of the float module. Installation instructions are provided in the following steps.
Figure 7.24: Float Indicator Cable
A - Longer Covered Cable Section
1788
–
1800 mm (70-3/8
–
70-7.8 in.)
B - Uncovered Middle Cable Section
C - Shorter Covered Cable Section
1352
–
1364 mm (53-1/4
–
53-11/16 in.)
Summary of Contents for FlexDraper FD1 Series
Page 2: ...FD1 Series FlexDraper Header Published June 2018...
Page 12: ......
Page 42: ......
Page 45: ...214685 33 Revision A Figure 4 6 Filler Cap 10 Install filler cap A SETTING UP FLOAT MODULE...
Page 72: ......
Page 116: ......
Page 166: ......
Page 336: ......
Page 350: ......
Page 353: ......