Checking the Facility Outlets and Power Source:
CAUTION:
Do not touch the receptacle or the receptacle faceplate with anything other than your test probes
before you have met the requirements in “Checking the Facility Outlets and Power Source” below.
Performing the following will ensure that appropriate power will be used by the pSeries 670. The following
checklist is for reference purposes, and will likely be performed by a service engineer prior to installation.
__ 1. The pSeries 670 is equipped to use 200-240 V / 380-415 V / 480 V ac, three-phase. Check that
the correct power source is available.
__ 2. Before system installation, locate and turn off the branch circuit CB (circuit breaker). Attach tag
S229-0237, which reads “Do Not Operate.”
Note:
All measurements are made with the receptacle faceplate in the normally installed position.
__ 3. Some receptacles are enclosed in metal housings. On receptacles of this type, perform the
following steps:
a. Check for less than 1 volt from the receptacle case to any grounded metal structure in the
building, such as a raised-floor metal structure, water pipe, building steel, or similar structure.
b. Check for less than 1 volt from receptacle ground pin to a grounded point in the building.
Note:
If the receptacle case or faceplate is painted, be sure the probe tip penetrates the paint and
makes good electrical contact with the metal.
__ 4. Check the resistance from the ground pin of the receptacle to the receptacle case. Check
resistance from the ground pin to building ground. The reading should be less than 1.0 ohm, which
indicates the presence of a continuous grounding conductor.
__ 5. If any of the checks made in substeps 2 and 3 are not correct, remove the power from the branch
circuit and make the wiring corrections; then check the receptacle again.
Note:
Do not use the digital multimeter to measure grounding resistance.
__ 6. Check for infinite resistance between the phase pins. This is a check for a wiring short.
CAUTION:
If the reading is other than infinity, do not proceed! You must make the necessary wiring
corrections to satisfy the above criteria before continuing. Do not turn on the branch circuit
CB until all the above steps are satisfactorily completed.
__ 7. Remove tag S229-0237, which reads “Do Not Operate.”
__ 8. Turn on the branch circuit CB. Measure for appropriate voltages between phases. If no voltage is
present on the receptacle case or grounded pin, the receptacle is safe to touch.
__ 9. With an appropriate meter, verify that the voltage at the outlet is correct.
__ 10. Verify that the grounding impedance is correct by using the ECOS 1020, 1023, B7106, or an
appropriately approved ground impedance tester.
__ 11. Turn off the branch circuit CB.
__ 12. Attach tag S229-0237, which reads “Do Not Operate.”
__ 13. You are now ready to install and connect the power cables to the pSeries 670.
Additional Installation Considerations:
In the United States, installation must be made in accordance
with Article 645 of the National Electric Code (NEC). In Canada, installation must be in accordance with
Article 12-020 of the Canadian Electrical Code (CEC).
Dimensions and Weight
Physical Characteristic
Slimline Doors
Acoustical Doors
Height
2025 mm (79.72 in.)
2025 mm (79.72 in.)
Chapter 1. Reference Information
97
Summary of Contents for pSeries 670
Page 1: ...pSeries 670 Service Guide SA38 0615 03 ERserver...
Page 2: ......
Page 3: ...pSeries 670 Service Guide SA38 0615 03 ERserver...
Page 12: ...x Eserver pSeries 670 Service Guide...
Page 16: ...xiv Eserver pSeries 670 Service Guide...
Page 18: ...xvi Eserver pSeries 670 Service Guide...
Page 324: ...Yes Go to Step 154A 14 on page 302 304 Eserver pSeries 670 Service Guide...
Page 718: ...698 Eserver pSeries 670 Service Guide...
Page 848: ...L3 Cache Shorts Test Step 4 828 Eserver pSeries 670 Service Guide...
Page 849: ...L3 Cache Shorts Test Step 5 Chapter 9 Removal and Replacement Procedures 829...
Page 851: ...L3 Cache Shorts Test Step 2 Chapter 9 Removal and Replacement Procedures 831...
Page 853: ...L3 Cache Shorts Test Step 4 Chapter 9 Removal and Replacement Procedures 833...
Page 854: ...L3 Cache Shorts Test Step 5 834 Eserver pSeries 670 Service Guide...
Page 971: ...7040 Model 671 Media Subsystem 1 2 3 4 5 6 7 8 9 10 Chapter 10 Parts Information 951...
Page 973: ...Power and SCSI Cables to the Media Subsystem 1 2 3 5 4 6 Chapter 10 Parts Information 953...
Page 986: ...966 Eserver pSeries 670 Service Guide...
Page 990: ...970 Eserver pSeries 670 Service Guide...
Page 1018: ...998 Eserver pSeries 670 Service Guide...
Page 1020: ...1000 Eserver pSeries 670 Service Guide...
Page 1028: ...1008 Eserver pSeries 670 Service Guide...
Page 1031: ......