GREE GMV5 HR HEAT RECOVERY UNITS
127
(2) Make sure that the commissioning software is correct before commissioning.
(3) The professional aftersales commissioning software provided by GREE should be used for
commissioning of GREE VRF system.
(4) Make sure that all required files and parameter records are prepared.
3.2 Pre-commissioning Check
Installation environment check covers the heat exchange environment of unit and electromagnetic
radiant components. All requirements should comply with national and local electrical standards. For any
installation incompliance, records should be made for providing an analysis basis during refrigerating
system testing.
3.2.1 Installation Appearance Check
Installation appearance check covers whether pipeline installation complies with specifications,
whether refrigerant pipes and condensing drainage pipes are thermal insulated, and whether
Refrigerant pipes should be tidily installed, with outdoor and indoor disperse pipes leaning in the
required scope. For any installation incompliance, records should be made for providing an analysis
basis during refrigerating system testing.
Refrigerant pipes and condensing drainage pipes should not be exposed. If any pipe is exposed, an
immediate amendment is required to avoid serious loss.
3.2.2 Refrigerating System Check
(1) Before commissioning, make sure that the stop valve of each module reaches the maximum
opening degree. Check whether there is any refrigerator oil leakage around the valve. If there is,
immediately check for leakage with soap bubbles or leak detectors. If confirming that leakage
exists, immediately stop commissioning and solve the problem before continuing
commissioning.
Does the stop valve of
outdoor unit reach the
maximum opening
degree?
Oil
leakage?
(2) Check system refrigerants before startup
Before the system is started, connect the liquid-tube valve of ODU with a high pressure gauge and
the air-tube valve of ODU with a low pressure gauge, and then read their values. In this case, high
pressure and low pressure of the system should be in balance status, and the difference between the
saturation temperature corresponding to the balanced pressure value and the environment temperature
(the higher in outdoor and indoor temperatures is taken as environment temperature) should not be
Содержание GC201808-III
Страница 36: ...GREE GMV5 HR HEAT RECOVERY UNITS 32 Circuit diagram of GMV Q144WM B1 F U Circuit diagram of GMV Q168WM B1 F U ...
Страница 87: ...GREE GMV5 HR HEAT RECOVERY UNITS 83 1 External Connection for Individual Units ...
Страница 92: ...GREE GMV5 HR HEAT RECOVERY UNITS 88 ...
Страница 227: ...GREE GMV5 HR HEAT RECOVERY UNITS 223 Troubleshooting ...
Страница 286: ...GREE GMV5 HR HEAT RECOVERY UNITS 282 Troubleshooting ...
Страница 314: ...GREE GMV5 HR HEAT RECOVERY UNITS 310 4 Loosen the screws on the compressor drive as shown in the figure below ...
Страница 362: ...JF00302879 ...