Commissioning
3.8
Commissioning of the "Table positioning" technology application
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Commissioning steps
Below find a description of the commissioning steps of the "Table positioning" application shown in
illustration
.
Please observe the sequence of the steps in the following chapters and follow them through
carefully. This will help you to commission your inverter quickly and as safely as possible:
Prepare inverter for commissioning
Creating an »Engineer« project & going online
Parameterising the motor control
Save parameter settings safe against mains failure
Enable inverter and test application