Performing the commissioning (using Axis 1 as an example)
Parameter manual
b maXX
BM5800
Document No.: 5.16029.03
Baumüller Nürnberg GmbH
46
2.6
48
Click on the "Stop/Off" button in the Drive Manager dialog.
49
The motor will then stop.
50
Switch the pulse enabling off.
Saving the data
set
This data set should now be saved.
51
Click on the "Dataset management" icon in the icon bar.
52
Click on the "Save All" button in the Dataset management.
Figure 30:
ProDrive: Dataset management
53
Wait until "
OK
" is displayed under "Data Set State"
At this point the data set is saved in Flash memory.
Switching off the
drive
To conclude the commissioning, the drive is switched off.
54
Disconnect the device from the main power supply and the control voltage using the
appropriate switching elements.
This successfully completes the commissioning for Axis 1.
In the same way, you can set the parameters for Axis 2 and start it up from
Содержание b maXX BM5800
Страница 10: ...Parameter manual b maXX BM5800 Document No 5 16029 03 Baumüller Nürnberg GmbH 10 of 814 Contents ...
Страница 724: ...Monitoring Parameter manual b maXX BM5800 Document No 5 16029 03 Baumüller Nürnberg GmbH 724 of 814 3 11 ...
Страница 756: ...Error descriptions Parameter manual b maXX BM5800 Document No 5 16029 03 Baumüller Nürnberg GmbH 756 of 814 4 5 ...
Страница 800: ...Parameter manual b maXX BM5800 Document No 5 16029 03 Baumüller Nürnberg GmbH 800 of 814 ...
Страница 808: ...Parameter manual b maXX BM5800 Document No 5 16029 03 Baumüller Nürnberg GmbH 808 of 814 ...
Страница 814: ...Parameter manual b maXX BM5800 Document No 5 16029 03 Baumüller Nürnberg GmbH 814 of 814 Notes ...
Страница 815: ......