DIB-500 R4.1
Installation
Connecting equipment racks (as of 5 carriers)
74
Installation and Operation Manual 90DIB500IM02 – 5.2
Electric shock when touching live parts. Hardware components in the equipment
cabinet are live.
➔
When performing work in the equipment cabinet, ensure that the voltage source on
site is switched off.
1. Connect the voltage supply cable to the LRU according to the labelling, refer to Fig-
Figure 4.13 Interfaces of the LRU
2. Clamp the LRU onto the top hat rail from above. The catch must snap in audibly.
✓
The installation of the LRU has thus been completed.
4.4.2.6
Installing the top hat rail power supply unit
The top hat rail power supply unit must be connected to the top hat rail.
Figure 4.14 shows the position of the top hat rail power supply unit on the top hat rail.
Figure 4.14 Top hat rail power supply unit on the top hat rail
brown
white