8.2 Periodical visual inspections
The table below lists the recommended tasks for maintaining the products. The visual
inspections should be performed in the intervals specified to be able to respond in due
time, e.g. in the case of changes at the location that may result in improper operation.
We recommend logging the results of the inspection.
Replacing (network, hardware) components
If faults occur or if the (network, hardware) components are damaged, the respective
(network, hardware) components including the installed software components may have
to be replaced. The replacement of (network, hardware) components is described in the
document entitled "Service and Maintenance Manual".
Table 8.2
Tasks to be performed during visual inspections and intervals
Task/s
Interval/s
Site inspection based on the document "Site Requirements“, such
as the inspection of the:
|
Grounding facility
|
Voltage supply connection
|
Installation location of the GPS antenna
|
Condition and fit of all the supply lines and replacement of
supply lines as required.
Upon location changes
Once every three months
Check the condition of the product in respect of:
|
Readiness for operation
|
Dirt and dust accumulations on and in the equipment rack,
clean if required.
|
Check the degree of soiling of the contact pins, remove any
dirt if required.
|
Proper operation of the fan unit; replace the air filter pad as
required.
Once every three months
Check connected external alarms
Once every three months