6
Power-On Commissioning
6.1 Vacuumizing and Precharging Refrigerant
CA UTION
Ensure that no combustion-supporting materials (air or additives) enter the smart
cooling product system during commissioning. Huawei shall not be liable for any
risks and losses thus incurred.
6.1.1 Requirements on the Filling Amount of Refrigerant and
Refrigerant Oil
●
Refrigerant is R410A.
●
The refrigerant oil is MEL32.
Sufficient refrigerant oil has been filled in the indoor unit compressor before
delivery to ensure reliable running of the 100 m long pipeline and low
temperature component. No refrigerant oil needs to be added during onsite
installation. If the compressor is damaged, replace it with a new one. The
refrigerant oil has been pre-filled into the compressor. No refrigerant oil needs
to be added. Add refrigerant oil as required only when the refrigerant oil leaks
and the compressor does not need to be replaced.
NO TICE
If one NetCol8000-A090D is used with two NetCol500-A060s (or one NetCol500-
A120) and the length (L) is 80 m, fill 29 kg R410A for each compressor system
and 58 kg R410A in total for one NetCol8000-A090D. Formula: 9.4 + (80 – 10) x
0.28= 29
NetCol8000-A(045, 055, 060, 090, 120) In-room Air
Cooled Smart Cooling Product
User Manual
6 Power-On Commissioning
Issue 05 (2020-10-10)
Copyright © Huawei Technologies Co., Ltd.
154