Expected Result
Actual Result
No open or short circuits, or incorrect connections occur in
electrical loops.
□ Passed □ Failed
The power cables for the indoor and outdoor units, signal
cable, teamwork cable, and T/H sensor cable are
connected as required.
□ Passed □ Failed
The rated specifications of the upstream general circuit
breaker meet the maximum current requirement.
□ Passed □ Failed
All cables, connectors, and screws are secured.
□ Passed □ Failed
Devices are properly grounded.
□ Passed □ Failed
5.2 Outdoor Unit Installation Verification
Table 5-4 Check items of the outdoor unit after installation
Check
Item
Expected Result
Actual Result
Rack
The rack is installed properly, without any
tilt.
□ Passed □ Failed
The rack is secured to the ground or base.
Fans
The fans are secured, and the blades rotate
without block.
□ Passed □ Failed
Electric
control
box
The electrical control box is secured.
□ Passed □ Failed
The screws on the cover of the electrical
control box are tightened.
Cables are properly connected.
Waterproof connectors are secured and
properly sealed.
Air
tightness
of the
heat
exchanger
There is a sound of air flow when you press
the needle valve.
□ Passed □ Failed
Fins of the
heat
exchanger
The fins are not pushed down or damaged.
□ Passed □ Failed
Fins protection plates have been removed.
Pipes
Pipes are secured and not damaged.
□ Passed □ Failed
The needle valve cap has been tightened.
NetCol8000-A(045, 055, 060, 090, 120) In-room Air
Cooled Smart Cooling Product