B. Install a Breather Hose Assembly
Detail Steps/Work Items
Key Items/References
(1)
Assemble breather hose assembly:
S
Install the short breather line to the breather
outlet adaptor and secure with worm drive
clamp.
S
Install the long breather line to the breather
outlet adaptor and secure with worm drive
clamp.
Refer to Figure 1.
Make sure to install the breather outlet
adapter with correct orientation.
(2)
Install the breather hose assembly according to
the previously marked attachment points.
(3)
Connect the breather hose assembly to the
outlet at the top aft side of the injector cover and
guide tube. Secure both connections with worm
drive clamps.
(4)
Secure the breather hose assembly with cable
ties and P-clamps according to the previously
marked attachment points.
(5)
Install the engine cowlings.
Refer to Section 71-10.
(6)
Connect the airplane main battery.
Refer to Section 24-31.
Summary of Contents for DA 42 NG
Page 933: ...AIRCRAFT DA 42 NG AMM Fuel Doc 7 02 15 Rev 4 28 TITLE Page 1 15 Mar 2018 CHAPTER 28 FUEL ...
Page 1459: ...AIRCRAFT DA 42 NG AMM Lights Doc 7 02 15 Rev 4 33 TITLE Page 1 15 Mar 2018 CHAPTER 33 LIGHTS ...
Page 1711: ...AIRCRAFT DA 42 NG AMM Doors Doc 7 02 15 Rev 4 52 TITLE Page 1 15 Mar 2018 CHAPTER 52 DOORS ...
Page 1853: ...AIRCRAFT DA 42 NG AMM Wings Doc 7 02 15 Rev 4 57 TITLE Page 1 15 Mar 2018 CHAPTER 57 WINGS ...
Page 2071: ...AIRCRAFT DA 42 NG AMM Engine Doc 7 02 15 Rev 4 72 TITLE Page 1 15 Mar 2018 CHAPTER 72 ENGINE ...
Page 2288: ......
Page 2320: ......
Page 2322: ......