Installation and commissioning flowchart
Task
See
Identify the frame size of your drive: R0…R4.
:
on page
Plan the installation: select the cables, etc.
Check the ambient conditions, ratings and required
cooling air flow.
Planning electrical installation
on page
on page
Unpack and check the drive.
:
page
If the drive will be connected to an IT (ungrounded) or
corner grounded system, check that the internal EMC
filter is not connected.
:
on page
Install the drive on a wall or in a cabinet.
on page
Route the cables.
Planning electrical installation
on page
Check the insulation of the input cable and the motor
and the motor cable.
on page
Connect the power cables.
on page
Connect the control cables.
on page
Check the installation.
Commission the drive.
Start-up, control with I/O and ID Run
on page
Summary of Contents for ACS350 Series
Page 1: ...ACS350 User s Manual ACS350 Drives 0 37 22 kW 0 5 30 HP ...
Page 4: ......
Page 8: ...Safety 8 ...
Page 18: ...Table of contents 18 ...
Page 24: ...Hardware description 24 ...
Page 44: ...Installation checklist 44 ...
Page 56: ...Start up control with I O and ID Run 56 ...
Page 140: ...Program features 140 ...
Page 242: ...Actual signals and parameters 242 ...
Page 266: ...Fieldbus control with embedded fieldbus 266 ...
Page 284: ...Fault tracing 284 ...
Page 288: ...Maintenance and hardware diagnostics 288 ...
Page 309: ...Dimensions 309 Frame size R2 IP20 NEMA 1 3AFE68586658 A Frame size R2 IP20 NEMA 1 VAR EMC ...
Page 311: ...Dimensions 311 Frame size R3 IP20 NEMA 1 3AFE68579872 B Frame size R3 IP20 NEMA 1 VAR EMC ...
Page 313: ......