ESIE15-08B
|
Part 3. Repair
1. General Repair procedures
19/07/16
Page 107
Daikin Altherma Monobloc CA
1.1.2. Refrigerant pump down
This unit is equipped with an automatic pump down operation which will collect all refrigerant from the field piping and hydro-box
in the outdoor unit. To protect the environment, make sure to perform the following pump down operation when relocating or
disposing of the unit.
1.1.2.1 Outdoor unit
1.
Remove the valve lid from liquid stop valve and gas stop valve.
2.
Carry out forced cooling operation by pressing SW3 on the service PCB.
3.
After 5-10 min (after only 1-2 min in case of very low Ta < -10°C), close the liquid stop valve with a hexagonal wrench.
4.
Check on the manifold if vacuum is reached.
5.
After 2-3 minutes, close gas stop valve and stop forced cooling operation by pressing forced cooling operation switch SW3 on
the service PCB again.
I
NFORMATION
The outdoor unit is equipped with a low pressure sensor to protect the compressor by switching it off.
Never short-circuit the low pressure sensor during pump down operation!