114
5.2. Test
without load
Before you perform test without load, first remove the load of the servo motor (including the
unit, coupling on the shaft, accessories, etc.). After all the load is removed, first check if the
motor can run normally by normal operation procedure. And then connect to all the load
back.
The following introduces the motor test without load.
5.2.1.
JOG test without load
JOG operation is available only when no alarm occurs.
Ensure that SON-SG is open-circuit (SON OFF) when testing.
Ensure that EMG, LSP, LSN are on , and if CN1 has no external wiring, you can
perform this function by using PD01.
JOG without load can be performed by the panel or Shihlin communication software, it is to
confirm whether the speed and direction of motor are as expected. You cannot modify the
motor speed by the panel during JOG test, JOG test and its speed can only be modified by
Shihlin communication software via RS-485 or USB transmission, and it is recommended to
run JOG test at low speed. Below introduces JOG test of panel screen operation.
Step 1: connect servo drive and motor correctly, and then apply power to the servo drive.
Step 2: press the MODE button on the panel to enter the diagnosis screen, and then press
the UP button 3 times to enter TEST1 (JOG mode). At this time, press and hold SET
button for 2 seconds to switch to d-01. screen (JOG test operation).
Press UP button 3 times
Press and hold SET button for more than 2 seconds
JOG operation is enabled when this screen shows
The LED is flicking when JOG test starts
Содержание SDP Series
Страница 33: ...20 400V series DC 24V Power supply Note terminal P N cannot be grounded ...
Страница 42: ...29 2 CN1 connector male Front view Side view Rear view CN1 wiring terminal on the back of CN1 1 26 50 25 ...
Страница 45: ...32 4 The last step is to fasten the screw of housing ...
Страница 203: ...190 It is recommended that the user performs torque position mode switching after motor is stopped completely ...
Страница 385: ...372 ...
Страница 405: ...392 ...
Страница 499: ...486 SME L040 SME L075 SME L100 SME L150 ...
Страница 500: ...487 SME L200 SME L300 SME M100 SME M150 ...
Страница 509: ...496 When the load reaches 300 the operation time is 5 51 seconds ...
Страница 541: ...528 Middle inertia power cable Middle inertia 2KW 3KW 400V High inertia power cable 1 8KW 2 9KW 4 4KW 5 5KW 7 5KW ...
Страница 555: ...542 14 5 Manual version and revision history Manual version V1 00 Release month July 2022 ...