Step 2 Check the eLight function.
Table 5-6 Function commissioning
Check Method
Normal Connection Status
Choose Maintenance > Configuration
Wizard > Linkage Test > eLight
Controller Commissioning and click
Test.
The eLight is lit up in red, green, blue,
and white in sequence for 3 seconds
respectively, and then turns off.
Step 3 Set eLight parameters.
1. Log in to the ECC800-Pro WebUI as an administrator.
2. In the Smart Module View, click Modify Device. Select an eLight actuator
under Devices, drag it to the access actuator to which you want to bind the
eLight actuator, and click Exit Edit Mode.
Figure 5-9 eLight actuator position