- 77 -
-
77
-
6-2 Test Run
(3) Operation preparation
After confirmation of test run and normal operation confirmation of motor, please implement the
connection with the mechanical system.
1 Please set the function codes related to machine action.
2 Check the interface matched with peripheral mechanical equipment.
(4) Operation confirmation
Before delivery, various functions of the inverter have been set up as shown in the function code list.
If change of settings of operation command is required, please refer to [5-6 Basic Operation] for
implementation.
(5) Operation methods besides commands from operation panel
■Operation by commands from external signals
1 When controlling operation / stop according to external signals, please set the function code F1101 to 2,
that is, F1101 = 2.
If FR(Forward) signal is ON, then the inverter will drive to forward. If RR(Reverse) signal is ON, then the inverter
will drive to reverse. Moreover if RREV(Reverse revolution) is ON, then the inverter will drive to reverse
revolution from revolution direction command. Therefore if both input signals FR(Forward) and RREV(Reverse
revolution) are ON at the same time, then the inverter will drive to reverse. If both input signals RR(Reverse) and
RREV(Reverse revolution) are ON at the same time, then the inverter will drive to forward.
Figure 6-2 External operation command action
2 When carrying out frequency setting by external potentiometer, 4
-
20mA, 0
-
10V etc., please set the
function code F1002 = 2
-
20.
3 Please refer to [4-6 Connection Diagram of Control Circuit Terminals] for correct use of external signals.
FR
Time
RR
R
EV
FWD
RREV
Frequency
Содержание SVCO6
Страница 1: ...High Performance Vector Control Inverter Instruction Manual SANKEN ELECTRIC CO LTD ...
Страница 2: ......
Страница 324: ... 322 Memorandum ...
Страница 325: ......