- 66 -
6
–1
Operation Steps
6-1
Operation Steps
The following flowchart shows all the operation steps before and after operation of the inverter.
Please follow the following flow chart to carry out test run.
6-2-1 Confirmation Before
Power Input
6-2-2
Confirmation
After
Power Input
6-2-3 Basic Setting (1)
6-2-4 Motor Control Mode
6-2-5 Basic Setting (2)
6-2-6 Motor Parameter Auto
Tuning
6-2-7 Basic Setting (3)
6-2-8 Operation Confirmation
Figure 6-1 Operation step flow
Motor control mode
Set up installation wiring
inspection before power
input
Inspection after power
input
Rated settings
F1320
Basic function setting
Basic function setting
Basic function setting
Auto torque boot?
Auto tuning
F1001
V/f control mode
Sensorless control mode
External command
Operation panel setting
External control
terminal setting
Operation panel setting
Frequency command
External control
terminal setting
Application
function setting
Prepration starts
Preparation ends
Control mode with
sensor
F1001=1 V/f control
F1001=2,4 without speed
sensor(select speed control or torque
control)
F1001=3,6 with a speed
sensor (select speed control
or torque control)
Test run
F2007=0
Control terminal use
Control terminal use
F2007=1,2