Installation
SiEN34-705
48
General Information
Grouped Drain
Piping
1. It is standard work practice to make connections to the main pipe from above. The pipe
down from the combination should be as large as possible.
2. The pipework should be kept as short as possible and the number of indoor units per group
kept to a minimum.
Use of an
Auxiliary Drain
Hose (Flexible)
If a drain pan made of polystyrene foam is used then an auxiliary drain hose (flexible) is also
essential. A flexible drain hose permits the drain socket and drain pipe to be connected without
difficulty and prevents any undue strain being placed on the drain pan.
Important points
1. The drain pipe should be at least equal in size to that of the indoor unit.
2. The drain pipe is thermally insulated to prevent the formation of condensation inside the
pipe.
3. The drain up mechanism should be fitted before the indoor unit is installed and when the
electricity has been connected some water should be added to the drain pan and the drain
pump checked to see that it is functioning correctly.
4. All connections should be secure. (Special care is needed with PVC pipe)
The use of a colored adhesive with PVC pipes will help you to remember to connect them
up.)
Grouped drain pipes from multiple units
Face piping
downward
Face the vent pipe mounth
downward to keep foreign
matter from penetrating
yhe system
Vent pipe
30 or more
Indoor unit
Thermal insulation (band area)
Drain pan
Metal clamp
Thermal insulation (drain pipe area)
Auxiliary drain hose
Indoor unit
Indoor units
Use widest diameter possible
Hanger pitch
1~1.5m
Insulation material
Gradient of
1:100 or more
Hanger
Содержание RXYQ5PY1
Страница 2: ......
Страница 287: ...SiEN34 705 Heat Pump 60Hz RXYQ5 54P Installation Manual 281...
Страница 292: ...Heat Pump 60Hz RXYQ5 54P SiEN34 705 286 Installation Manual...
Страница 339: ...Operation Manual SiEN34 705 332 Operation Manual...